Question 4.

A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?

A
B
C
D

Question Explanation

Text Explanation

Let the desired efficiency of each worker '6x' per day.

140*6x*200= 6 km ...(i)

In 60 days 60/200*6=1.8 km of work is to be done but actually 1.5km is only done.

Actual efficiency 'y'= 1.5/1.8 *6x =5x.

Now, left over work = 4.5km which is to be done in 140 days with 'n' workers whose efficiency is 'y'.

=> n*5x*140=4.5 ...(ii)

(i)/(ii) gives,

(1406x200)(n5x140)\frac{(140⋅6x⋅200)}{(n⋅5x⋅140)}=64.5\frac{6}{4.5}

=> n=180.

.'. Extra 180-140 =40 workers are needed. 

Video Explanation
No video explanation yet — we're on it and uploading soon!
XAT 2026 Full Course - Enroll Now for Best XAT Preparation
CAT LRDI 100 Recorded Course - Master Logical Reasoning and Data Interpretation
HOME
XAT Sankalp Sale
Quant Revision Book
More
YoutubeWhatsapp