Question 22.

John takes twice as much time as Jack to finish a job. Jack and Jim together take one-thirds of the time to finish the job than John takes working alone. Moreover, in order to finish the job, John takes three days more than that taken by three of them working together. In how many days will Jim finish the job working alone?

A
B
C
D

Question Explanation

Text Explanation

Let Jack take tt days to complete the work, then John will take 2t2t days to complete the work. So work done by Jack in one day is 1t\frac{1}{t} and John is 12t\frac{1}{2t}.

Now let Jim take mm days to complete the work. According to question,

1t+1m=32t\frac{1}{t} + \frac{1}{m} = \frac{3}{2t} or 1m=12t\frac{1}{m} = \frac{1}{2t}

or

m=2tm = 2t Hence Jim takes 2t2t time to complete the work.

Now let the three of them complete the work in pp days. Hence John takes p+3p+3 days to complete the work.

12t(m+3)=42tm\frac{1}{2t}(m+3) = \frac{4}{2t}m

or

12t(m+3)=42tm\frac{1}{2t}(m+3) = \frac{4}{2t}m

or m=1m=1. Hence Jim will take (1+3)=4(1+3)=4 days to complete the work. Similarly John will also take 4 days to complete the work.

Video Explanation
No video explanation yet — we're on it and uploading soon!
XAT 2026 Full Course - Enroll Now for Best XAT Preparation
CAT LRDI 100 Recorded Course - Master Logical Reasoning and Data Interpretation
HOME
XAT Sankalp Sale
Quant Revision Book
More
YoutubeWhatsapp