Question 16.
A group of N people worked on a project. They finished 35% of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N is
A
23
B
140
C
36
D
150
Question Explanation
Text Explanation
Video Explanation
Let the unit of work done by 1 man in 1 hour and 1 day be MDH unit (Man Day Hour).
Thus, in 7 hours per day for 10 days, the work done by people =
MDH units.
Since this is equal to 35% of the total work,
35% of the total work = MDH units.
Total work = MDH units.
The work left = MDH units.
Now, 10 people left the job. So, the number of people left =
Since people completed the rest of work in 14 days by working 10 hours a day,
(N−10)×14×10=130N