Question 9.

One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is

A
12
B
11.5
C
12.5
D
10

Question Explanation

Text Explanation

Let Rahul work at a units/hr and Gautam at b units/hour

Now as per the condition :

8a+6b =7.5a+7.5b

so we get 0.5a=1.5b

or a=3b

Therefore total work = 8a +6b = 8a +2a =10a

Now Rahul alone takes 10a/10 = 10 hours.